Share, email, print, bookmark SOURCE reports.

[broadstreet zone=”80100″]

FRAMINGHAM – The following is a list of road construction projects in the City of Framingham including Framingham DPW, state projects, and utility work.

All projects will be conducted in conformance with the health and safety protocols set forth by the Commonwealth and the City of Framingham.

As the situation with COVID-19 is ever-changing, construction schedules are subject to change.

Work is weather permitting.

Beaver Street Bridge: Bridge work continues. Beaver Street Bridge will be closed to through traffic and pedestrians until Fall 2020. A detour will be in effect at all times.

Bosworth Road Gas Main Relay – Eversource Gas: Eversource Gas will continue relaying gas main and services on Bosworth Road. A one-way alternating traffic pattern will be in effect. Expect minor delays.

Cedar Street Gas Main Relay – Eversource Gas: Eversource Gas will begin installing gas service lines on Cedar Street. A one-way alternating traffic pattern will be in effect. Expect minor delays.

[broadstreet zone=”59982″][broadstreet zone=”59983″][broadstreet zone=”59984″]

[broadstreet zone=”58610″]

Eames Street and Pratt Street Gas Main Relay – Eversource Gas: Eversource Gas will continue installing gas service lines on Eames Street and Pratt Street. A one-way alternating traffic pattern will be in effect. Expect delays at times.

Eversource Gas Corrosion Prevention: Eversource Gas will continue installing corrosion prevention measures at various locations. Expect minor delays. Police details will be on-site to facilitate traffic.

Grant Street Road and Sidewalk Rehabilitation: Sidewalk and road rehabilitation continues on Grant Street (between Arthur Street and Clinton Street). A lane shift and/or detours will be in effect at times. Police details will be on-site to facilitate traffic. Expect moderate delays. 

[broadstreet zone=”70106″]

Hampden, Hillcrest, and Berkshire Water Main Replacement: The Water Division will begin installing a temporary water bypass on Hampden Road in preparation for water main replacement. Hampden Road will be accessible to residents and emergency vehicles at all times.  

Highgate Street/Indian Head Road Drainage Inspection: The Highway Division will be conducting a drainage inspection between Highgate Street, Indian Head Road, and Summer Street. Police details will be on-site to facilitate traffic. Expect minor delays.

Marble Street Roadway Improvements: Punch list items. Expect minor delays.

Nobscot Intersection Improvements: Utility poles will be set, and electrical wires will be transferred in preparation for the intersection improvements project. Expect minor delays at times.

[broadstreet zone=”70107″]

By editor

Susan Petroni is the former editor for SOURCE. She is the founder of the former news site, which as of May 1, 2023, is now a self-publishing community bulletin board. The website no longer has a journalist but a webmaster.