Share, email, print, bookmark SOURCE reports.

[broadstreet zone=”53130″]

FRAMINGHAM – The following is a list of road construction projects in the City of Framingham during the week of September 19, 2021

The projects include City of Framingham and utility projects.

All work is weather permitting.

***

Berry Street Gas Main Replacement: Eversource gas will continue replacing gas main on Berry Street. Expect minor delays. A one-way alternating traffic pattern will be in effect. 

[broadstreet zone=”58610″]

Carlson Road Water, Sewer, and Roadway Improvements: Water main installation. Expect minor to moderate delays. A one-way alternating traffic pattern will be in effect on Carlson Road and Glen Street. Also, at times, a one-way alternating traffic pattern will also be in effect on Beaver Street and Kendall Avenue.

Edgell Road and Edmands Road Gas Main Replacement: Eversource gas will continue replacing gas main on Edgell Road and Edmands Road. Expect moderate delays. Lane shifts and/or a one-way alternating traffic pattern will be in effect.
 
Grove Street Roadway and Drainage Improvements (Between Edmands Road and Winch Street): Begin making drainage improvements on Grove Street. Expect moderate delays. A lane shift and/or a one-way alternating traffic pattern will be in effect.

[broadstreet zone=”70106″]

Nobscot Intersection Improvements: Underground and aerial fire alarm cable work continues. Culvert work continues. Expect minor delays. Police details will be on-site to facilitate traffic as needed.
 
Roadway Maintenance – Crack Sealing: A specialized contractor will crack seal the following roads: Franklin Street, Dudley Road, Potter Road, and Brook Street. Expect minor delays. Police details will be on-site to facilitate traffic.

[broadstreet zone=”59982″]

School Street Sidewalk Improvements (Between Old Connecticut Path and Hamilton Street): Punch-list items. Expect minor to moderate delays at times. A lane shift and/or one-way alternating traffic will be in effect.

Taralli Terrace Sidewalk and Roadway Improvements: Sidewalk work will begin. Expect moderate delays. A lane shift and/or a one-way alternating traffic pattern will be in effect.


 

 

By editor

Susan Petroni is the former editor for SOURCE. She is the founder of the former news site, which as of May 1, 2023, is now a self-publishing community bulletin board. The website no longer has a journalist but a webmaster.