FRAMINGHAM – The following is road construction work scheduled in the City of Framingham this week. It includes City of Framingham, Framingham DPW, MassDOT, and Eversource work.

Construction schedules are weather permitting and subject to change.

[broadstreet zone=”59947″]

Blackberry Lane Sewer Pump Station: Pump station and sewer main work continues. Blackberry Lane at Millwood Street will be closed to through traffic during work hours and a detour will be in effect. Please seek an alternate route.

Cochituate Rail Trail – Route 30/Cochituate Road: Sidewalk and curbing improvements will be made. Roadway milling in preparation for paving is scheduled for Thursday, July 15. Lane shifts will be in effect, expect moderate delays.

Edgell Road Gas Main Replacement: Eversource gas will continue replacing gas main on Edgell Road between the Nobscot intersection and Donovan Drive. Expect moderate delays. Lane shifts and/or a one-way alternating traffic pattern will be in effect.

[broadstreet zone=”59982″]

Gilbert Street Gas Main Installation: Eversource gas will continue replacing gas main on Gilbert Street between Nipmuc Road and Winthrop Street. Expect minor delays. A one-way alternating traffic pattern will be in effect.

Grant Street Roadway and Sidewalk Improvements (Between Arthur and Hartford Streets): Sidewalk excavation and curbing work. Expect minor to moderate delays. A two-way and/or one-way alternating traffic pattern will be in effect. Police details will be on-site to facilitate traffic.

Leland Street Sidewalk and Road Improvements (Between Irving and Beaver Streets): Punch-list items. Expect minor delays.

[broadstreet zone=”59983″]

Mt. Wayte Avenue Gas Main and Regulator Pit Replacement (Between Union Avenue and Franklin Street) – Eversource Gas: Eversource will continue gas main work on Mt. Wayte Avenue. Expect moderate delays. A partial road closure will be in effect on Mt. Wayte Avenue eastbound. Traffic traveling eastbound will be detoured.

Nobscot Intersection Improvements Project: Underground electrical service work continues. Anticipated work will occur off the road. Expect minor delays.