FRAMINGHAM – The following are City of Framingham, MassDOT, and utility projects planned this week, June 20, 2021.
Construction schedules are weather permitting and subject to change.
Blackberry Lane Sewer Pump Station: Utility work continues. Expect moderate delays. A detour or alternating traffic pattern will be in effect during construction.
Blandin Avenue Roadway Improvements (Between Beaver Street and Marble Street): A section of Blandin Avenue will be milled and paved on Tuesday-Wednesday, June 22-23, 2021. Expect moderate delays. Seek an alternate route.
Edgell Road Gas Main Replacement: Eversource gas will continue replacing gas main on Edgell Road between the Nobscot intersection and Donovan Drive. Expect moderate delays. Lane shifts and/or a one-way alternating traffic pattern will be in effect.
[broadstreet zone=”59984″]
Gilbert Street Gas Main Installation: Eversource gas will continue replacing gas main on Gilbert Street between Nipmuc Road and Winthrop Street. Expect minor delays. A one-way alternating traffic pattern will be in effect.
Grant Street Roadway and Sidewalk Improvements (Between Arthur and Hartford Streets): Milling and paving are scheduled for Monday-Wednesday, June 21-23, 2021. Sidewalk excavation continues as well. Expect moderate delays. A two-way and/or one-way alternating traffic pattern will be in effect. Police details will be on-site to facilitate traffic.
Leland Street Sidewalk and Road Improvements (Between Irving and Beaver Streets): Driveway apron adjustments, pavement markings, and punch-list items. Expect minor delays. Police details will be on-site to facilitate traffic.
[broadstreet zone=”59983″]
Mt. Wayte Avenue Gas Main and Regulator Pit Replacement (Between Union Avenue and Franklin Street) – Eversource Gas: Eversource will continue gas main work on Mt. Wayte Avenue. Expect moderate delays. A partial road closure will be in effect on Mt. Wayte Avenue eastbound. Traffic traveling eastbound will be detoured.
Nelson Street and Forest Avenue Water Main Replacement: Water main replacement continues. Nelson Street and Forest Avenue will be open to residents and emergency vehicles only during construction.
Osmose Utility Citywide Utility Pole Inspections and Restoration – Verizon: Dig safe paint markings will be noticeable in the public right-of-way near telephone poles throughout the City for Osmose’s Citywide utility pole inspections and restoration.