FRAMINGHAM – The following are the City of Framingham road and utility construction project the week of May 23.

Construction schedules are weather permitting and subject to change.

Edgell Road Gas Main Replacement: Eversource gas will continue replacing gas main on Edgell Road between the Nobscot intersection and Donovan Drive. Expect moderate delays. Lane shifts and/or a one-way alternating traffic pattern will be in effect.

[broadstreet zone=”70107″]

Gilbert Street Gas Main Installation: Eversource gas will continue replacing gas main on Gilbert Street between Nipmuc Road and Winthrop Street. Expect minor delays. A one-way alternating traffic pattern will be in effect.

Leland Street Sidewalk and Road Improvements (Between Irving and Beaver Streets): Sidewalk and drainage work continues. Final paving is tentatively scheduled for Thursday, May 27. A detour will be in effect during paving operations, expect delays, please seek an alternate route. For the rest of the week, a two-way and/or one-way alternating traffic pattern will be in effect. Police details will be on-site to facilitate traffic. 

Mt. Wayte Avenue Gas Main and Regulator Pit Replacement (Between Union Avenue and Franklin Street) – Eversource Gas: Eversource will continue gas main work on Mt. Wayte Avenue. Expect moderate delays. A partial road closure will be in effect on Mt. Wayte Avenue eastbound. Traffic traveling eastbound will be detoured.

[broadstreet zone=”59982″]

Nelson Street and Forest Avenue Water Main Replacement: A City hired contractor will begin preparations for water main replacement. Nelson Street and Forest Avenue will be open to residents and emergency vehicles only during construction. 

Newton Place Water Main Replacement: Trench paving and punch-list items. Newton Place will be open to residents and emergency vehicles only during construction.

Nobscot Intersection Improvements: Eversource Electric will excavate the road to transfer electrical wires on Edmands Road. Expect moderate delays. A two-way and/or one-way alternating traffic pattern will be in effect.

Warren Road, Walnut Street, and Dennison Avenue Surface Treatments: Utility castings will be adjusted. Expect minor delays. Police details will be on-site to facilitate traffic.