Image by Manfred Richter from Pixabay
Share, email, print, bookmark SOURCE reports.

[broadstreet zone=”59946″]

ASHLAND – Construction on Pond Street (Route 126) continues in Ashland this week.

Northern Construction will continue the road construction between the Holliston/Ashland Town Line and Eliot Street. 

Eversource Gas / Mirra Construction should complete the gas main work between Algonquin and Nickerson Road today, May 19.

After, two crews will continue the work. One crew will work towards the Framingham end and the second crew will begin the gas main replacement at the intersection of Pond and Eliot. 

[broadstreet zone=”59982″]

Part one of this work will occur during the day; located on the “East” side of Pond Street. Approximately 250 feet of main needs replacing in this particular section of road. The work hours will be from 7 a.m. to 3 p.m.. The start time will be adjusted if traffic is drastically impacted. 

Eversource and the Town are reviewing the Road Opening Permit. This work may start as early as Friday, May 21 

It will take one to two weeks to complete. 

In early June, Eversource will perform gas work at night on the “west” side (Shaw’s) of Eliot Street. The start date is to be announced.

[broadstreet zone=”58610″]

By editor

Susan Petroni is the former editor for SOURCE. She is the founder of the former news site, which as of May 1, 2023, is now a self-publishing community bulletin board. The website no longer has a journalist but a webmaster.