FRAMINGHAM – The following is a list of road & utility construction projects in the City of Framingham the week of May 16, 2021.
Construction schedules are weather permitting and subject to change.
Edgell Road Gas Main Replacement: Eversource gas will continue replacing gas main on Edgell Road between the Nobscot intersection and Donovan Drive. Expect moderate delays. Lane shifts and/or a one-way alternating traffic pattern will be in effect.
Gilbert Street Gas Main Installation: Eversource gas will continue replacing gas main on Gilbert Street between Nipmuc Road and Winthrop Street. Expect minor delays. A one-way alternating traffic pattern will be in effect.
[broadstreet zone=”59983″]
Leland Street Sidewalk and Road Improvements (Between Irving and Beaver Streets): Sidewalk work continues. A two-way and/or one-way alternating traffic pattern will be in effect. Police details will be on-site to facilitate traffic.
Trench Paving – Stevens Road and a section of Mt Wayte Avenue, Grace Street, Chappellwood Road, McAdams Road, and Brigham Road
Trench milling and paving are scheduled for Monday-Tuesday, May 17-18. Expect minor to moderate delays. Police details will be on-site to facilitate traffic.
Mt. Wayte Avenue Gas Main and Regulator Pit Replacement (Between Union Avenue and Franklin Street) – Eversource Gas: Eversource will continue gas main work on Mt. Wayte Avenue. Expect moderate delays. A partial road closure will be in effect on Mt. Wayte Avenue eastbound. Traffic traveling eastbound will be detoured.
[broadstreet zone=”59946″]
Newton Place Water Main Replacement: Water main replacement continues. Newton Place will be open to residents and emergency vehicles only during construction.
Nobscot Intersection Improvements: Eversource Electric will continue to relocate aerial wires on Water Street. Expect moderate delays. A two-way and/or one-way alternating traffic pattern will be in effect.
Sanitary Sewer Evaluation Survey (SSES), Phase 6: Sewer main pipe investigations will be conducted on Gates Road and Rockridge Road. Expect minor delays.
Saxonville Intersection Design: Soil investigations will be conducted on Central Street, Concord Street, Elm Street, and Water Street. Expect minor delays at times.
Warren Road, Walnut Street, and Dennison Avenue Surface Treatments: A City-hired contractor will apply surface treatments to Warren Road, Walnut Street, and Dennison Avenue on Monday and Tuesday, May 17-18. Traffic will be detoured in one direction while operations are conducted. Please seek an alternate route.