ASHLAND – Motorists should expect road construction on Route 126 (Pond Street) due to the revitalization project in Ashland.

Monday 4/5 & Tuesday, 4/6: Remove Guiderail by nursing home

Monday 4/5- Wednesday 4/7: Test Drilling

Monday 4/5- Thursday 4/8: Activity in Shaw’s parking lot

Monday 4/5- Friday 4/16:

  • Heavy activity on Eliot Street as crews excavate for a wall
  • Gas Work beginning at Nickerson Road and Continuing to Algonquin Road
  • Installing Utility Poles

Tuesday 4/6 – Friday, 4/9: Installing temporary fencing barrier on Pond Street by Eliot Street

Wednesday 4/7- Tuesday 4/13: Drainage by Algonquin Trail

Wednesday 4/14- Friday 4/16: Drainage by Eliot Street heading toward Holliston Town Line