FRAMINGHAM – The following are the road construction projects in Framingham this week, July 26. Work includes road, gas main, water & sewer main, and other projects.

All projects will be conducted in conformance with the health and safety protocols set forth by the Commonwealth and the City of Framingham. As the situation with COVID-19 is ever-changing, construction schedules are subject to change.

All work is weather permitting.

Beaver Street Bridge: Bridge work continues. Beaver Street Bridge will be closed to through traffic and pedestrians until Fall 2020. A detour will be in effect at all times.

Belvidere Avenue Gas Main Relay – Eversource Gas:
Eversource Gas will begin installing gas service lines on Belvidere Avenue. A one-way alternating traffic pattern will be in effect. Expect minor delays.

[broadstreet zone=”80100″]

Chestnut Street Gas Main Relay – Eversource Gas:
Eversource Gas will continue relaying gas main on Chestnut Street.A one-way alternating traffic pattern will be in effect. Expect delays at times.

Eames Street and Pratt Street Gas Main Relay – Eversource Gas: Eversource Gas will begin installing gas service lines on Eames Street and Pratt Street. A one-way alternating traffic pattern will be in effect. Expect delays at times.

Flagg Drive Water Main Replacement
: Water main installation continues. A one-way alternating traffic pattern will be in effect. Expect delays at times.

[broadstreet zone=”59982″][broadstreet zone=”59983″][broadstreet zone=”59984″]

Grant Street Gas Main Relay: Eversource Gas will begin relaying gas main on Grant Street. A one-way alternating traffic pattern will be in effect. Expect delays at times.

Hillcrest and Berkshire Water Main Replacement:
The Water Division will begin installing water main on Berkshire. Berkshire Road will be open to residents and emergency vehicles only.

Nobscot Intersection Improvements: Verizon and Eversource will continue to set new utility poles in preparation for the intersection improvements project. Expect minor delays at times.

Saxony Sewer Improvements
: The Sewer Division will continue making sewer improvements near Saxony Road/Saxony Terrace. Expect minor delays at times.

[broadstreet zone=”70106″][broadstreet zone=”70107″]

Urban Street Sweeping Program – Area D: The Highway Division will street sweep Area D on Tuesday, July 28. NO PARKING will be allowed from 9 AM to Noon. Vehicles parked on the street will be ticketed and towed. 

The following streets will be swept during this operation: Beaver Court, Beaver Park Road, Beaver Street, Beaver Terrace Circle, Coolidge Street, First Street, Interfaith Terrace, Marian Road, Morton Street, Picard Terrace, Second Street, Taralli Terrace, Third Street, and Willis Street.

Warren Road and Brigham Road Gas Main Relay – Eversource Gas: Eversource Gas will continue relaying gas main and installing services on Warren Road and Brigham Road.A one-way alternating traffic pattern will be in effect. Expect delays at times.