Update on Oregon Road Water Replacement Project

ASHLAND – The contractor on June 18 and 19 installed water services from the new water main to the service valve at the property line for residents on Oregon Road.

Once connected, the contractor will need to gain access to the house to flush the service.

Once all services are completed, the contractor will remove the above ground temporary main and hoses.

The temporary pavement will remain for a period of time to allow potential settling of the back fill material.

Them the contractor will return to remove the temporary pavement and install permanent pavement.

Any questions or concerns call Ashland DPW.